At the moment, metal structures are completed up to the 4th floor.
Concrete core is completed up to the 13th floor and for the 14th floor 30% is completed.
The flight of stairs inside the elevator shaft is set to the level of the 11th floor.
Concrete staircases up to the 11th floor is completed.
In the meantime, a 55-second video showing the 31 days of MARR Tower works during August
is available on the MARR Group YouTube channel.