The concrete slab for the concrete core is completed until the 17th floor.
The 5th floor of the metal structure (metal structure and concrete slabs) is also completed as well as the majority of works for the metal structure of the 6t and 7th floors.
In the meantime, a 55-second video showing the 31 days of MARR Tower works during December is available on the MARR Group YouTube channel.