In Cyprus, August is traditionally a holiday month. However, while everyone else was chilling at the beach, works at the MARRTower construction site continued. Several important steps were completed during this final month of summer, such as:
– casting of the lift shaft on the 10thfloor, with casting works continuing on the 11thand 12thfloors;
– casting of basement and mezzanine slabs;
– installation of the 1stfloor fireproof steel frame which is the substructure of the main floors;
– installation of the staircase on the 8thfloor (5thapartment floor). At this height there is a stunning sea view –whichMARRTower residents and their guests will be enjoying before long.
In the meantime, a 55-second video showing the 31 days of MARR Tower works during August is available on the MARR Group YouTube channel.
For additional information on the project, please call +357 8000 4050 or send us an e-mail to [email protected]
In the meantime, a 55-second video showing the 31 days of MARR Tower works during August is available on the MARR Group YouTube channel.
For additional information on the project, please call +357 8000 4050 or send us an e-mail to [email protected]